In May, CU Boulder Today announced the construction of a new building on campus, the Center for Academic Success and Engagement, or CASE building, which will be built atop the Euclid Autopark.
Site staging begins on schedule on Monday, Aug. 1. Construction crews will be on-site to start preliminary work.
Site staging includes:
- FencingÌýaround the entire construction siteÌý
- Re-striping of Euclid AvenueÌý
- Trailers and equipment placed on site
- Rerouting of pedestrian and bike paths
- Closure and reduction of widthÌýof some sidewalks around the Euclid Autopark.
Euclid Autopark will remain open at this time and up through student move-in week. Construction begins Aug. 22.
You can view the construction staging/mobilization plan.
New CASE Building Timeline
July 15: Tree removal is complete
July 18: Bike station and rack relocation is complete
Aug. 1: Site staging begins
Fencing, trailers and equipment go into place.
Aug. 22: Construction begins
Euclid Autopark will remain open at this time, but there will be intermittent parking space closures between Aug. 22 and October.
Oct. 10 - Jan. 13, 2017: Euclid AutoparkÌýclosure
During this time, campus visitors will be directed to park in Lot 204 across the street from Euclid Autopark. Affected permit holders will receive direct correspondence from Parking and Transportation Services regarding any possible relocations. Once reopened, the top level of the garage will have a slightly different traffic flow which will be well-marked for patrons. The garage is scheduled to be reopened by the start of spring classes on Jan. 17, 2017.